The Question Exactly Appeared In The Actual PMP Exam.

You are a project manager for a construction project. Only 85% of the total works has completed, and the project spent the budget due to the change in the cost of materials. If the material cost was US $ 7. 00, and your estimate is US $ 10.00. If the cost of the materials has reached US $ 16.00, what should your estimation of the material have been to prevent this situation? Continue reading “The Question Exactly Appeared In The Actual PMP Exam.”